What are the key components of legislation related to air quality management?

Click to see answer

p.1

Key components of air quality management legislation typically include:

  1. Standards and Regulations: Establishing permissible levels of pollutants.
  2. Monitoring and Reporting: Requirements for regular monitoring of air quality and reporting findings.
  3. Permitting: Regulations governing emissions from industrial sources.
  4. Enforcement: Mechanisms for ensuring compliance with air quality standards.
  5. Public Participation: Provisions for community involvement in air quality management decisions.

Click to see question

1 / 95
p.1
Legislation on Air Quality

What are the key components of legislation related to air quality management?

Key components of air quality management legislation typically include:

  1. Standards and Regulations: Establishing permissible levels of pollutants.
  2. Monitoring and Reporting: Requirements for regular monitoring of air quality and reporting findings.
  3. Permitting: Regulations governing emissions from industrial sources.
  4. Enforcement: Mechanisms for ensuring compliance with air quality standards.
  5. Public Participation: Provisions for community involvement in air quality management decisions.
p.3
Dust Control Measures

What is the purpose of the ETWB Technical Circular in relation to dust control on construction sites?

The ETWB Technical Circular provides guidelines and standards for managing dust emissions during construction activities, ensuring compliance with air quality regulations and minimizing environmental impact.

p.3
Common Violations in Construction

What are some common violations related to dust control in construction?

Common violations include failing to implement dust suppression measures, not maintaining equipment properly, and neglecting to monitor dust levels as required by regulations.

p.3
Partnership Programs in Construction

What role do partnership programs play in dust control at construction sites?

Partnership programs facilitate collaboration between construction companies, regulatory bodies, and the community to promote best practices in dust control and enhance compliance with environmental standards.

p.3
Dust Abatement Techniques

What are some examples of effective dust control measures that can be implemented on construction sites?

Effective dust control measures include:

  1. Water spraying to dampen surfaces
  2. Use of dust suppressants
  3. Installation of windbreaks
  4. Regular cleaning of construction sites
  5. Properly covering materials during transport.
p.4
Environmental Management Plan

What is the purpose of the Environmental Management Plan in public works contracts?

The Environmental Management Plan aims to manage environmental impacts by outlining strategies for waste management, abatement of nuisances, and implementing necessary environmental measures such as wheel washing systems and dust/smoke screens.

p.4
Environmental Management Plan

What types of contracts require the preparation and implementation of an Environmental Management Plan?

The Environmental Management Plan is required for all public works contracts, specifically for capital works contracts exceeding $20 million and with a contract period longer than 6 months.

p.4
Environmental Management Plan

What are some components included in the Environmental Management Plan?

Components of the Environmental Management Plan include:

  1. Waste Management Plan
  2. Abatement of nuisances
  3. Payment for EMP documentation, environmental walks, training, etc.
  4. Payment for environmental measures such as wheel washing systems and dust/smoke screens.
p.5
Air Pollution Control Regulations

What are the requirements for fuel used in construction according to the Special Condition of Contract?

  • Use ultra low sulphur diesel (ULSD) with a sulphur content of less than 0.005%.
  • Maintain a delivery record of ULSD.
  • Conduct a fuel sample analysis for sulphur content by a HOKLAS laboratory.
p.5
Air Pollution Control Regulations

What are the key components of the air pollution abatement measures specified in the Particular Specification?

  • Designated environmental personnel to oversee compliance.
  • Implementation of air pollution abatement measures such as:
    • Screens/enclosure
    • Water spraying system
    • Vacuum cleaning device
  • Ensure smoke from construction plant does not exceed Shade 1 on the Ringelmann Chart for more than 30 seconds.
  • Use of an auto wheel washing machine.
  • Installation of a mechanical cover.
  • Development of an Environmental Management Plan.
p.6
Environmental Management Plan

What are the key components of an effective environmental management plan for construction activities?

An effective environmental management plan for construction activities should include:

  1. Tendering for dust control equipment
  2. Designated personnel responsible for overseeing environmental practices
  3. Pollution prevention strategies rather than just abatement measures
  4. Structured training programs to enhance environmental awareness among workers
p.6
Dust Abatement Techniques

What is the difference between pollution prevention and abatement in the context of construction activities?

  • Pollution Prevention: Focuses on reducing or eliminating the generation of pollutants at the source, thereby minimizing environmental impact.
  • Abatement: Involves controlling or reducing pollution after it has been created, often through treatment or cleanup methods.
p.6
Training and Awareness in Environmental Practices

Why is environmental awareness training important in construction activities?

Environmental awareness training is crucial in construction activities because it:

  • Educates personnel on the impact of construction on the environment.
  • Promotes compliance with environmental regulations.
  • Encourages proactive measures to prevent pollution.
  • Enhances the overall sustainability of construction practices.
p.6
Complaint Statistics and Analysis

What trends can be observed from the complaints against construction activities from 2001 to 2011?

The bar chart indicates trends in complaints against construction activities over the years:

  • Total complaints show fluctuations, with a peak in certain years.
  • Water, Waste, Noise, and Air complaints vary, indicating specific areas of concern.
  • The overall trend can help identify which types of complaints are most prevalent and may require targeted interventions.
p.7
Dust Abatement Techniques

What are the main purposes of the Air Pollution Control (Construction Dust) Regulation?

The main purposes are to:

  1. Employ effective dust abatement measures to reduce dust emission.
  2. Reduce air nuisance.
  3. Improve general air quality.
p.7
Common Violations in Construction

What are the three main types of construction works classified under the Air Pollution Control (Construction Dust) Regulation?

The three main types of construction works are:

  1. Notifiable work: Includes building demolition, construction of superstructure, site formation, reclamation, etc.
  2. Regulatory work (Notification not required): Includes road opening/resurfacing, external renovation, slope stabilization.
  3. Excluded work (Notification not required): Includes internal renovation, specified processes, etc.
p.8
Dust Control Measures

What types of work are considered notifiable under the Air Pollution Control Ordinance?

The following types of work are considered notifiable:

  1. Site formation
  2. Reclamation
  3. Work carried out in any part of a tunnel that is within 100 m of any exit to the open air
  4. Road construction work
  5. Demolition of a building
  6. Construction of building foundation
  7. Construction of building superstructure
p.9
Dust Control Measures

What types of work are included in Part III of the dust control schedule?

In Part III of the dust control schedule, the following types of work are included:

Type of WorkIncluded in Part III
Notifiable WorkYes
Regulatory WorkYes
Excluded WorkYes
p.10
Dust Control Measures

What should be done if there is a breakdown of air pollution control equipment at a construction site?

The relevant plant or dusty process should be stopped immediately.

p.10
Dust Control Measures

What is prohibited when cleaning off dust at a construction site?

Using a compressed air jet to clean off dust is prohibited.

p.10
Dust Control Measures

What facilities should be provided at a construction site for vehicle washing?

Vehicle washing facilities should be provided, and the area between the site exit and the vehicle washing facilities should be paved.

p.10
Dust Control Measures

What is the required height for hoarding along the site boundary?

A hoarding of 2.4 meters should be provided along the site boundary.

p.11
Dust Control Measures

What are the recommended measures for maintaining a main haul road to prevent dust accumulation?

  1. Pave the road with concrete, bituminous materials, or hard cores to minimize dust.
  2. Keep the road clear of dusty materials.
  3. Maintain the entire road surface wet to suppress dust.
p.11
Dust Control Measures

What specific action should be taken for roads leading only to a construction site regarding dust management?

Clear dusty materials from the portion of the road within 30 meters of the vehicle entrance and exit to prevent dust from being carried onto the road.

p.12
Dust Control Measures

What is the requirement for storing bagged cement exceeding 20 bags?

Bagged cement exceeding 20 bags should be covered or enclosed in an area sheltered on the top and the three sides.

p.12
Dust Control Measures

What should be avoided when storing cement bags?

Cement bags should not be stored in an open area.

p.12
Dust Control Measures

What is the recommended storage condition for cement bags?

Cement bags should be stored in a sheltered area, preferably under a cover.

p.12
Dust Control Measures

What is the storage requirement for bulk cement or Pulverised Fuel Ash (PFA)?

Bulk cement or PFA should be stored in a closed silo equipped with a high-level alarm.

p.13
Dust Abatement Techniques

What are the recommended methods for treating exposed earth after construction activities?

The recommended methods for treating exposed earth include:

  1. Compaction
  2. Hydroseeding
  3. Vegetation planting

These treatments should be completed within 6 months after the last construction activity.

p.13
Dust Control Measures

What are the disposal requirements for dusty materials collected by fabric filters or other equipment?

Dusty materials should be:

  • Disposed of in enclosed containers.
  • Not stored in open areas to prevent dust emissions.
p.14
Dust Control Measures

What are the control requirements for stockpiling dusty materials?

  1. Cover entirely by impervious sheeting.

  2. Place in an area sheltered on the top and the 3 sides.

  3. Maintain the entire surface wet.

p.15
Dust Control Measures

What is the recommended method for controlling dust when loading or unloading dusty materials?

Wet dusty materials with water spraying prior to operation.

p.15
Dust Control Measures

What are the key steps to ensure effective dust control when transferring dusty materials using a belt conveyor system?

  1. Enclose the belt conveyor from the top and the 2 sides.

  2. Enclose the transfer point between conveyors.

  3. Install belt scraper and bottom plates.

  4. Maintain vertical distance between belt conveyor outlet and material landing point at <1 m.

  5. Enclose the unloading area.

p.16
Dust Control Measures

What is the procedure for washing vehicles before leaving a construction site?

Wash every vehicle to remove dusty materials from the body and wheels before leaving the site.

p.16
Dust Control Measures

What should be done to loads of dusty materials on vehicles?

Cover any load of dusty materials to prevent dust emissions during transport.

p.16
Dust Control Measures

What is the recommended method for controlling dust during drilling, cutting, and polishing activities?

Continuously spray the surface with water to control dust emissions during these activities.

p.16
Dust Control Measures

What equipment should be used to manage dust during drilling operations?

Equip drilling machines with an effective dust extraction and filtering device to minimize dust emissions.

p.17
Dust Control Measures

What are the key steps for proper debris handling on a construction site?

  1. Cover or store debris in an area sheltered on the top and the 3 sides.

  2. Enclose the debris chute.

  3. Wet debris before dumping into the chute.

p.17
Dust Control Measures

What is the recommended practice for maintaining surface wetness during excavation or earth moving operations?

Spray the working area with water or chemicals before, during, and immediately after the operation to maintain the entire surface wet.

p.18
Dust Control Measures

What are the requirements for carrying out de-bagging, batching, and mixing of cement and PFA?

The process must be conducted in an area that is sheltered on the top and the 3 sides.

p.18
Dust Control Measures

What should be done to the working area before, during, and after operations at a construction site?

The working area should be wet to minimize dust. Additionally, all demolished items must be covered or placed in a sheltered area within a day of demolition.

p.19
Dust Control Measures

What is the requirement for wet areas before blasting?

A wet area must be maintained within 30 meters before blasting.

p.19
Dust Control Measures

Under what conditions is blasting not permitted?

Blasting is not permitted during a strong wind signal or tropical cyclone warning No.3 or above, unless permitted by the Commissioner of Mines.

p.20
Dust Control Measures

What measures should be taken to treat or seal stockpiles of dusty materials near a construction site?

Stockpiles of dusty materials greater than 1.2 m high and less than 50 m from the site boundary should be treated or sealed with bitumen or other suitable surface stabilizers.

p.20
Dust Control Measures

What are the recommended practices for dust control during the demolition of a building?

  1. Wet the working area prior to, during, and immediately after demolition.

  2. Enclose the building with impervious dust screens to a height of at least 1 m higher than the building.

  3. Wet remaining dusty materials after removal and clear the road surface.

p.21
Dust Control Measures

What is an effective measure to control dust during the construction of a superstructure?

Provide an effective dust screen where scaffolding is erected.

p.21
Dust Control Measures

What should be done to manage dust when using a skip hoist in construction?

Enclose the skip hoist to manage dust effectively.

p.22
Dust Control Measures

What measures should be taken to control dust during renovation on the outer surface of external walls or roofs?

  • Provide dust screens where there is scaffolding.
  • Enclose the skip hoist.
  • Wet remaining dusty materials after removal and clear the road surface.
p.22
Dust Control Measures

What are the key dust control practices during road opening resurfacing work?

  • Cover dusty materials.
  • Spray, remove, backfill, or reinstate dusty materials within 24 hours.
  • Ensure dusty materials do not extend beyond pedestrian barriers, fencing, or traffic cones.
  • Wet and clear any remaining dusty materials from the road surface after removal.
p.23
Common Violations in Construction

What types of road construction work are exempt from hoarding requirements?

  • Road construction work
  • Slope stabilization (if the site boundary adjoins road for vehicular traffic)
p.23
Common Violations in Construction

What exemptions apply to road opening or resurfacing work?

Road opening or resurfacing work is exempt from:

  • Vehicle washing facilities
  • Hoarding requirements
p.23
Common Violations in Construction

Under what circumstances is emergency work exempt from regulations?

Emergency work is exempt when:

  • There is a threat to human life or building safety.
  • Immediate repair of utility services, road collapse, or road blockage due to accidents.
p.24
Penalties for Non-Compliance

What are the penalties for failing to notify the Authority for notifiable work on the first and second convictions?

For the first conviction, the penalty is Level 4 (25,000)∗∗.Forthesecondorsubsequentconviction,thepenaltyis∗∗Level5(25,000)**. For the second or subsequent conviction, the penalty is **Level 5 (50,000).

p.24
Penalties for Non-Compliance

What are the penalties for failing to adopt dust control measures for notifiable work on the first and second convictions?

For the first conviction, the penalty is Level 5 (50,000)∗∗.Forthesecondorsubsequentconviction,thepenaltyis∗∗Level6(50,000)**. For the second or subsequent conviction, the penalty is **Level 6 (100,000) + 3-month imprisonment. Additionally, there is a daily fine of $10,000.

p.24
Penalties for Non-Compliance

What are the penalties for failing to adopt dust control measures for regulatory work and excluded work on the first and second convictions?

For the first conviction, the penalty is Level 4 (25,000)∗∗.Forthesecondorsubsequentconviction,thepenaltyis∗∗Level5(25,000)**. For the second or subsequent conviction, the penalty is **Level 5 (50,000). There is also a daily fine of $5,000.

p.25
Common Violations in Construction

What is a common violation related to dust control during mechanical breaking or drilling?

No water spraying is allowed during mechanical breaking or drilling, which can lead to significant dust in the air.

p.25
Common Violations in Construction

What is a common violation regarding site boundaries in construction?

There should be hoarding along the site boundary to separate the construction area from the public sidewalk and street, but in this case, there is none.

p.26
Common Violations in Construction

What is a common violation related to the storage of cement or PFA on construction sites?

A common violation is having no cover for more than 20 bags of cement/PFA.

p.26
Common Violations in Construction

What is a common violation regarding the stockpiling of dusty materials on construction sites?

A common violation is having no cover for stockpile of dusty material.

p.27
Common Violations in Construction

What is a common violation related to vehicles leaving construction sites?

Vehicles are often not washed before leaving construction sites, which can lead to dust and debris being spread onto public roads.

p.27
Common Violations in Construction

What is a common violation regarding the transportation of dusty materials?

A common violation is that there is no cover for the load of dusty material in vehicles, which can contribute to air pollution and dust dispersion.

p.28
Common Violations in Construction

What is a common violation related to the production of concrete at construction sites?

Producing concrete not in a sheltered area, which exposes it to environmental elements, is a common violation.

p.28
Common Violations in Construction

What is a common violation regarding notification for construction works?

Not submitting a notification for notifiable works, such as failing to complete the required Air Pollution Control Ordinance form, is a common violation.

p.29
Partnership Programs in Construction

What are the key partnerships involved in the construction industry in Hong Kong?

The key partnerships in the construction industry in Hong Kong involve the Hong Kong Construction Association, various government departments, and educational institutions. These collaborations aim to enhance the industry's development and promote best practices.

p.29
Partnership Programs in Construction

What types of events are organized to promote the construction industry?

Events organized to promote the construction industry include seminars and conferences. These events often feature discussions on topics like Green Construction and provide a platform for industry stakeholders to share knowledge and innovations.

p.31
Partnership Programs in Construction

What are the key components of the EPD's work in relation to construction practices?

The key components of the EPD's work include:

  1. Licensing / Permits: Ensuring that construction activities comply with legal requirements.
  2. Complaint Investigations: Addressing concerns raised by the public regarding construction practices.
  3. Surprise Inspections: Conducting unannounced checks to ensure compliance with regulations.
  4. Enforcement Actions:
    • Advisory / Warning Letters / Record of Inspections: Providing guidance and documentation of compliance status.
    • Abatement Notices: Issuing notices to rectify non-compliance issues.
    • Prosecution: Taking legal action against violators.
  5. Workshops, Seminars: Educating stakeholders on safe construction practices and environmental protection.
p.32
Dust Control Measures

What is a common dust control measure at construction site entrances?

A vehicle washing facility at the site exit helps to minimize dust by ensuring that vehicles are clean before leaving the site. Additionally, the road surface can be paved and dampened with hose water to further reduce dust emissions.

p.33
Dust Control Measures

What is the importance of washing vehicles before leaving a construction site?

Washing vehicles before leaving a construction site is crucial to prevent the spread of dirt and debris to surrounding areas, which can lead to environmental pollution and potential violations of regulations. It also helps maintain the cleanliness of public roads and reduces the risk of accidents caused by debris.

p.34
Dust Control Measures

What is the importance of covering loads of dusty materials with impervious sheeting before leaving a construction site?

Covering loads of dusty materials with impervious sheeting is crucial to prevent dust emissions during transport. This practice helps to minimize air pollution, protects public health, and ensures compliance with environmental regulations.

p.35
Dust Control Measures

What are the methods used for wetting a haul road in construction sites?

  1. Water Tanker Truck: A mobile method where a water tanker truck sprays water on the haul road to suppress dust.

  2. Fixed Water Spray System: A stationary system that continuously sprays water onto the haul road to maintain moisture and reduce dust.

p.36
Dust Control Measures

What is the purpose of wetting haul roads with water tankers?

Wetting haul roads with water tankers helps to control dust emissions, improving air quality and safety for workers and nearby communities.

p.36
Dust Control Measures

What are the benefits of using a fixed water spray system on haul roads?

A fixed water spray system provides continuous dust suppression, reduces the need for manual watering, and ensures consistent application of water to maintain road conditions.

p.37
Dust Abatement Techniques

What is the purpose of using dust screens or netting at construction sites?

Dust screens or netting are used to control and minimize dust emissions during construction activities. They help to prevent dust from spreading into the surrounding environment, thereby protecting air quality and reducing health risks for workers and nearby residents.

p.37
Dust Control Measures

How does wetting of haul roads contribute to dust control?

Wetting of haul roads helps to suppress dust by adding moisture to the surface, which binds the dust particles together and prevents them from becoming airborne. This practice is essential in maintaining air quality and ensuring safe working conditions on construction sites.

p.38
Dust Control Measures

What is the purpose of using impervious sheeting in construction sites?

Impervious sheeting is used to control dust emissions, protect materials from weather conditions, and minimize environmental impact during construction activities.

p.38
Dust Control Measures

How does impervious sheeting benefit stockpiles of dusty materials?

Impervious sheeting covers stockpiles of dusty materials to prevent dust from becoming airborne, thereby reducing air pollution and protecting the surrounding environment.

p.40
Dust Control Measures

What is the purpose of using water spray during breaking operations in construction?

Water spray is used to control dust emissions during breaking operations, ensuring a safer and cleaner work environment.

p.40
Dust Control Measures

How does wetting and enclosing the breaking area help in construction activities?

Wetting and enclosing the breaking area helps to minimize dust emissions and improve safety by keeping the work area contained and reducing airborne particles.

p.40
Dust Control Measures

What equipment is typically used to control dust during small-scale road opening work?

A soaked mop is often used to control dust emissions during small-scale road opening work, along with water spray to keep the area damp.

p.41
Dust Control Measures

What is the purpose of a dust extraction device in external wall grinding?

The purpose of a dust extraction device in external wall grinding is to control dust emission, ensuring a cleaner and safer work environment by minimizing airborne particles during the grinding process.

p.42
Dust Control Measures

What is the purpose of water spray during building demolition?

Water is continuously sprayed on the breaking area to control dust and minimize air pollution during the demolition process.

p.42
Dust Control Measures

Why is water spray used during drilling operations?

Water is continuously sprayed on the drilling surface to suppress dust and improve visibility, ensuring a safer working environment.

p.43
Dust Control Measures

What is the purpose of using impervious sheeting in construction sites for slope stabilization?

The purpose of using impervious sheeting in construction sites for slope stabilization is to fully enclose the work area, which helps to minimize dust emissions and protect the surrounding environment from dust pollution.

p.43
Dust Control Measures

How does covering stockpiles of dusty materials with tarpaulin help in dust control?

Covering stockpiles of dusty materials with tarpaulin helps in dust control by preventing wind from displacing the materials, thereby reducing the amount of dust that can become airborne. It also protects the materials from moisture and contamination.

p.44
Dust Control Measures

What is the purpose of wetting soil prior to a transfer operation involving dusty materials?

Wetting soil prior to transfer helps to minimize dust generation during the operation, thereby reducing air pollution and improving safety for workers.

p.45
Environmental Management Plan

What is the importance of implementing an Environmental Management Plan in construction sites?

An Environmental Management Plan is crucial as it helps in minimizing environmental impacts, ensuring compliance with regulations, and promoting sustainable practices. It outlines strategies for managing dust, waste, and other environmental concerns effectively.

p.45
Environmental Management Plan

How can adopting Green Construction Practices benefit construction projects?

Adopting Green Construction Practices can lead to reduced environmental impact, improved resource efficiency, and enhanced worker safety. These practices often include using sustainable materials, reducing waste, and implementing energy-efficient processes.

p.45
Training and Awareness in Environmental Practices

Why is strengthening training and supervision important in construction dust control?

Strengthening training and supervision is vital to ensure that all workers are aware of dust control measures and best practices. Proper training helps in reducing dust emissions and enhances compliance with environmental regulations.

p.45
Dust Control Measures

What role does establishing a communication channel play in managing dust during construction?

Establishing a communication channel allows for effective coordination among workers, management, and stakeholders. It ensures that everyone is informed about dust control measures and can report issues promptly, leading to better management of dust emissions.

p.47
Air Pollution Control Regulations

What are some examples of air pollutants?

Air pollutants include any solid, particulate, liquid, vapor, objectionable odor, or gaseous substance emitted into the atmosphere.

p.48
Air Pollution Control Regulations

What constitutes air pollution according to the provided definition?

Air pollution is defined as an emission of air pollutants that is prejudicial to health, a nuisance, imperils safety or interferes with the normal operation of aircraft, or is determined to be air pollution under a technical memorandum.

p.48
Air Pollution Control Regulations

What is defined as 'Dark Smoke' in the Air Pollution Control (Smoke) Regulations?

'Dark Smoke' is defined as smoke which is as dark as or darker than shade 1 on the Ringelmann Chart.

p.48
Air Pollution Control Regulations

What are the criteria for smoke emissions to be considered an offence under the Air Pollution Control (Smoke) Regulations?

The criteria for smoke emissions to be considered an offence are:

  1. Smoke emission lasting more than 3 minutes continuously.
  2. Smoke emission lasting more than 6 minutes in any period of 4 hours.
p.49
Air Pollution Control Regulations

What is the purpose of the Micro-Ringelmann Chart in smoke assessment?

The Micro-Ringelmann Chart is used to visually assess the density of smoke emissions from sources such as industrial stacks. It provides a standardized method for comparing the opacity of smoke against defined density levels, helping to determine compliance with air quality regulations.

p.50
Air Pollution Control Regulations

What are the steps for conducting a smoke assessment using a chart?

  1. Hold the chart at arm's length and view the smoke through the slot provided.

  2. Ensure that the light shining on the chart is the same light illuminating the smoke being examined; for optimal results, the sun should be behind the observer.

  3. Match the smoke as closely as possible with the corresponding grid on the chart.